Our Muirhall site is located in the Clydesdale area of central Scotland, on open plateau ground between the villages of Auchengray and Tarbrax. In January 2008 the windfarm was granted planning approval by South Lanarkshire Council after a period of 34 months in the planning system, and is now ready for construction.
Through an innovative partnership arrangement with Lomond Energy, the project is unique in that it is the first windfarm in the area to be developed independently by a local landowner not only to diversify his and three neighbouring farms, but also to help develop the local community’s needs through a significant community benefit package.
It is anticipated that Muirhall Wind Farm will be producing clean, green electricity by the end of 2010.
Stallashaw Moss, near Auchengray, South Lanarkshire
| Jan - Jun 04 | Feasibility & environmental assessment |
| Mar 05 | Planning application submitted |
| Jan 08 | Planning application approved |
| Feb 08 to date | Pre-construction preparations |
Construction ready
6 turbines, each 125m to blade tip, 12MW capacity
Muirhall Farm (main landowner and developer)
Development Project Manager
Non-technical summary